Four vertical in-situ concrete shafts
Solingen-Ittertal
Germany
Project details
- Construction company: Dohrmann August GmbH
- Building owner: BRW Bergisch Rheinischer Wasserverband
- Construction time RSB: December 2021 – still in construction
- Dimensions:
shaft 18: 4,5 m diameter / 10,9 m height - Shaft 19: 6,0 m diameter / 14,7 m height
- Shaft B1: 7,0 m diameter / 9,2 m height
- Shaft B2: 6,0 m diameter / 13,0 m height
- Special features:
Four in-situ concrete shafts with inlets and outlets flush with the formwork and several flat areas.