Gravity foundations (GBF)
Karehamn
Sweden
Project details
- Customer: Jan De Nul n.v., Hofstade-Aalst
- Construction time RSB: March 2012 – December 2012
- System solution: Special formwork for 16 foundations
- Special features:
The gravity foundations are placed offshore in the sea at the position on the seabed, but they are produced in the port area. Several sets of formwork were used to produce the 16 foundations.