Primary clarifier Marl-West Germany

Round basin formwork systems

Project details

  • Customer: Eiffage Infra-Nordwest GmbH
  • Building owner: EGLV Lippeverband
  • Construction time RSB: January 2023 – May 2023
  • Capacity: 1.100 m³
  • Dimensions:
    Funnel: 60° 4.50m diameter at the top / 3.1m high
    Pool wall: 19.00m diameter / 4.2m height
  • Special features: The primary sedimentation tank was built in the existing structure so that the tank wall was only constructed on one side. There is also a DN 1000 inlet pipe in the hopper, which was installed with a perfect fit.
Primary clarifier Marl-West / Germany