Haus Aden mine Bergkamen Germany

Project details
- Customer: Eiffage Infra-Nordwest GmbH
- Owner: RAG Aktiengesellschaft
- Construction time RSB: Juliy2024 – December 2024
- Volume: –
- Dimensions:
Start shaft 16.0m diameter / 14.5m height
Target shaft 12.5m diameter / 16.8m height - Special features: A tunnel runs under the Datteln-Hamm Canal in Bergkamen, which is accessible on both sides via a vertical shaft. In the first section of both shafts, the circular formwork was provided with a flat section. Another special feature is a circumferential bracket, which was integrated into the circular formwork in the fourth construction section to avoid joints.