Drop tanks Göttingen Germany

Project details
- Customer: Konrad Leymann Bauunternehmen
- Building owner: Göttinger Entsorgungsbetriebe
- Construction time RSB: October 2023 – November 2023
- Capacity: 200m³
- Dimensions: 6,00m Diameter / 7.4m height
- Special features: The construction of a lowering tank differs from the usual method. First, the first section, including the cutting wedge, is concreted on the surface. The basin is then excavated on the inside using an excavator, causing the tank to lower under its own weight. A total of three sections were concreted, of which only one remains visible on the surface.