Digester

Kloten

Switzerland

Digesters Formwork systems

Project details

  • Construction company: Erne AG Bauunternehmung
  • Building owner: AKO Glattbrugg
  • Construction time RSB: September 2021 – still under construction
  • Dimensions:
    Volume: 2 x digester with 3000 m³ each
  • Funnel: 35° tilt / bottom diameter 1,5 m / top diameter 15,8 m
  • Cylinder: 15,8 m diameter / 11,5 m height
    conical roof: 35° tilt / bottom diameter 15,8 m / top diameter 7,9 m

    gas hood: 7,9 m diameter / 1,7 m height
  • Description:

    In this project, the pipe cellar is being realized under the prestressed reinforced concrete funnels. With the RSB funnel formwork, the funnels including all clamping boxes can be casted in one pour without joints and tie points. Due to good planning, the conical roofs can also be concreted with the RSB funnel formwork.


Funnel formwork by RSB Formwork Technology for the pipe cellar of the digester in Kloten

Contact us

Notes on the processing of your data

3 + 10 =

RSB Formwork Technology

Schilfweg 1 · 6972 Fußach · Austria

n

+43 (0) 5578 7960-400

Subscribe to newsletter